2017 Main Street Improvements

Print
Press Enter to show all options, press Tab go to next option

 

Due to its deteriorated condition, the sanitary sewer mains in the downtown core, under 49C Avenue and under 50 Avenue, from 53 Street to Highway 2A, are scheduled for replacement in 2017.

This project includes pedestrian and road safety improvements, along with parking and other functional enhancements to accommodate future growth.

Construction on this $6.75 million project is scheduled for April 24 through to the end of October 2017, with work proceeding in stages to minimize the impact on downtown businesses and residents. Sidewalks and businesses will be open during construction. Look for on-site signage for more information.

Do you live in the downtown area, or a member of the downtown business community, and have questions about this project? Please contact us at  downtown2017@lacombe.ca.

 